PGBT
Three horizontal lines signifying an index link

Acquisition of Land 1946

What is it?

Section 3 of the Acquisition of Land (Authorisation Procedure) Act 1946 allowed the Secretary of State (on the application of a local authority) to make an order extinguishing rights of way, under specified circumstances.

How does it work?

The rules were set out in sub-s(1) as:

1. Land is acquired under compulsory purchase powers, or will be acquired under compulsory purchase powers, or is acquired by agreement and by an authority when the compulsory purchase powers could have been used; and

2. There subsists over any part of the land a public right of way, not being a right enjoyable by vehicular traffic; and

3. The Minister is satisfied that a suitable alternative right of way has been or will be provided, or that the provision of one is not required.

An order under s.3 of the 1946 Act takes effect on being made, but there is provision for where the order is made in advance of the acquisition of the land as sub-s(1) also says:
“Provided that where a right of way is extinguished under this subsection at a date before the acquisition of the land in question is completed, then if at any time thereafter it appears to the Minister that the proposal to acquire the land has been abandoned, he shall by order direct that the right shall revive, without prejudice, however, to the making of a new order extinguishing the right.”

Constraints

As is common for Ministerial rights of way orders, the proposals must be advertised before the order is made. The public can object to the proposals for a period of 21 days after first publication of the proposals (sub-s(2)).

Sub-s(3) provides that if any objection to the proposal is duly made and is not withdrawn, the Minister shall, before making the order, cause a public local inquiry to be held.

Other Information

This Act was repealed and replaced by the Acquisition of Land Act 1981 and the powers in s.3 of the 1946 Act are now found in modified form in s.32 of the 1981 Act.

Example

Acquisition of Land orders have been made in the area near the following paths: North Mymms 22 and 23

Photograph of a fingerpost indicating a bridleway, with hedgerow in background

A Note About these pages

While every endeavour has been made to give accurate information, the law is complex, subject to different interpretations and subject to change. The contents of this website are offered to help registered supporters and general readers, but do not constitute formal legal advice.